Friday, 30 August 2013

Blue Bells August Update

Blue bells now 4 months old! And a lot has been achieved in the duration...
This is an update for the month of August 2013.

Project Start Date:                6th May 2013
Project Duration:                   70weeks
Project Completion Date:    11th September 2014
Time elapsed to date:          17weeks

Block H 

  • Reinforcement 100%
  • Cast 3FL slab
  • Walling 3FL 100%

Block J

  • Formwork to 3FL slab 100%
  • Reinforcement to 3FL slab 80%

Block K

  • Cast 2FL slab
  • Walling 3FL 80%

Block L 

  • Walling 2FL 100%
  • Formwork to 3FL slab 90%
  • Reinforcement to 3FL slab 30%

Block M 

  • Walling 2FL 100%
  • Formwork to 3FL slab 90%
  • Reinforcement to 3FL slab 30%

Block N

  • Walling 3FL 100%

Block P

  • Formwork to 2FL slab 100%
  • Reinforcement to 2FL slab 100%
  • Cast 2FL slab

Block Q 

  • Walling 2FL 100%
  • Formwork to 3FL slab 90%

Below are photos from the site so far...

Show house Kitchen

Sample Lounge view


So your lounge will look something like this...

Corridors to bedrooms


And work continues...


Large windows that facilitate lighting...

Sample Bedroom...


Block Q construction progress...

Block P construction so far...

Site view...

On top of one of the blocks...

Workers on site, attending to detail...


Block K construction progress...

Aerial view of the site...


Block H taking shape...

Block J under construction

Block 2nd floor under construction...

The walling...

More walls in creation...


Block M under construction...

Floor foundations...

Show house coming soon...


Casting of the slabs...

Show house creation... watch this space....

What wouldn't you do with that space!

Note the positioning of the window...


Water pipes of very high quality...


And we can always spare a moment to pose for a pic...


For your information, there are also shops up for grabs!!!

Welding works...

So, price is what you pay, value is what you get.
An investment should be done with credible, reliable and efficient partners!

Remember: Cheap can be very expensive!!!

Do not be left out! 

Get in touch...

Safaricom Investment Co-operativeTel:Office 0722 00 5627/0722 00 4802/ 0722 00 2084Email:  sic@safaricom.co.keSafaricom House HQ1 |Ground Floor|Waiyaki Way





Tuesday, 20 August 2013

Lukenya Open Day

The Lukenya open day was held on 20th July 2013.

In line with our core values of efficiency and effectiveness, Safaricom Investment Co-operative did take some of the potential buyers to the Lukenya parcels in Mavoko county.

It was a beautiful day.
Those who missed out on the trip can see the main highlights through the images below.

Lukenya- The subject of our visit


The terrain of the land


Land with natural vegetation


Front view of the parcel of land


The side view of the parcel


The trip...


The stop over...



The Resort in the neighborhood 

about 4 KMS to the parcel on sale


Part of the land in the neighborhood reserved for a golf course


The view of the Mua hills from the parcel on sale 

- A beautiful site to see!


Briefing time...



Ready to receive our guests....


And they were here!


And they walked around the parcel


More briefing was done and questions answered


Exact details of the parcels given...


More questions asked and answers given


And it was a day well spent!


And off they went... Decisions having been made!


Have you gotten yourself one?
Plots 70% sold!
Come while stocks last


For more details get in touch with us:
Safaricom Investment Co-operativeTel:Office 0722 00 5627/0722 00 4802/ 0722 00 2084Email:  sic@safaricom.co.keBlog:    http://sicinvestments.blogspot.com/Safaricom House HQ1 |Ground Floor|Waiyaki Way


Monday, 12 August 2013

Blue Bells July Updates

Dear Investors,

Three months of construction and this is where we are at!

Our contractors are working day and night to deliver quality and value.

We are working on having the show house ready in the next 1 month.

Time is running out, units are running out, get yourself one today!

2 bedrooms apartments going at Kshs. 6.2 M

3 bedrooms apartments going at Kshs. 6.6 M

For more information get in touch with us on: sic@safaricom.co.ke


Front view of the construction

Construction site view

Ground floor complete in some of the blocks

Works on the 1st floor continuing



Construction materials on site

Front view of some of the blocks

This may be your house, see how S.I.C pays attention to detail... 

Construction workers on site, no compromise on security standards

A foundation so strong!

The view of one of the blocks already taking shape!

Construction progress so far...

Construction progress so far...

Construction progress so far

Front view of the blocks

Block Q in the making...

Block N in the making...

The ground work

Block H will house the show house

Block H and J side by side

Block J front view

Block N aerial view 

Work in progress...

The laying of the stones, one by one done to precision!



Wood work for roofing purposes


The team working on Blue Bells apartments

Block H already at 2nd floor

The unfinished interior of the apartments



You can now start feeling your space and getting used to it!

See the position of the windows,
well positioned for lighting up your house!

This may be your living room!

Between the blocks!

The unfinished exterior of one of the apartments


The unfinished interior of one of the apartments


Bathroom and toilets under construction


Unfinished beauty!



Unfinished Interior

Unfinished Interior

Stare case access...


This is why the units are flying off the shelf...

Side view of one of the apartments

When we promise we deliver....

Don't miss out, be a part of this today when it is still affordable.
The going rate of such apartments currently is 10 M for 3 bedrooms and 8.5 M for 2 bedrooms.

For more information get in touch with us on: sic@safaricom.co.ke
Thank you for your continuous support.