Monday 8 July 2013

June Blue Bells Site Report

It has been exactly two months since the ground was broken at Blue Bells Gardens in Mlolongo.

Construction is underway for the first phase of the project.Bookings for the parcels still ongoing, with the prices for 3 bedrooms being at 6.6 million and for the two bedrooms being at 6.2 million.
This is the site progress report during the month of June

Block H
The ground floor walling in complete as well as the ground floor
columns. Form work to the first floor slab is done while fixing of
reinforcement to beams and slab is 50% complete.


Block J
The ground floor columns were cast and ground floor walling
has been completed. The fixing of form work to first floor slab is
in progress.


Block K
Back filling to foundation was completed, the BRC mesh and
DPM laid. Casting of the ground floor slab is ongoing.


Block L
Ground floor columns and walling was completed and fixing of
form work to first floor slab is now in progress.

Block M
Casting of the ground floor slab was done. Construction of
ground floor columns and walling is complete and currently
fixing of form work to first floor slab is ongoing.
Fixing of reinforcement to beams is also in progress.


Block N
Back filling was completed as well as anti-termite treatment,
laying of DPM and BRC and the ground floor slab cast. Walling
on the ground floor has also been completed.

Block P
The ground floor slab was cast, columns on the ground floor are
at 95% completion level and the ground floor walling is 95% done.
Skillman Construction Ltd Blue Bell Gardens

Block Q
Fixing of form work to first floor slab has commenced.


Front view of the construction site

Workers on site

Construction materials on site


Ground floor already up for some blocks

Aerial view of the site

Blocks ready for slabbing for first floor construction

Laying the foundation for the slab

Attention to details

The contractors making sure that the
 job is done to perfection

And the houses are up


Front view of the site

Material ready for use.

Construction material being prepared.


The Blue Bells site looks like this so far.


Grab yourself a unit if you are yet to.